Strategic Planning — Virtual AI Patient

5-Month Roadmap (March – July 2026)


1. What is Strategic Planning?

Strategic planning defines our long-term vision, major milestones, and resource allocation over the remaining project timeline. It answers:

  • What are we building by July 2026?
  • When will each major component be delivered?
  • Why are we prioritizing certain features over others?
  • How do we ensure we meet our goals despite risks?

For our project, strategic planning covers 5 months (March–July 2026) and breaks down the work into monthly phases with clear deliverables.


2. Strategic Overview

Timeline at a Glance

March      April      May        June       July
└────┬─────┴────┬─────┴────┬─────┴────┬─────┴────┬
Foundation   Core MVP    Medical    MVP        Final
             Complete    Workflow   Complete   Polish
     
EPIC-00      EPIC-01,02  EPIC-05,06 EPIC-07    Testing
EPIC-14      EPIC-03,04  EPIC-08,11 EPIC-10    Documentation
EPIC-13      EPIC-12                EPIC-09    Presentation

Key Milestones

Milestone Target Date Description Link to Milestone
Project Kickoff March 1, 2026 Team formed, repository created  
Foundation Complete March 31, 2026 Repo, CI/CD, basic prototype working https://github.com/virtual-ai-patient/platform/milestone/1
MVP Core Complete April 30, 2026 Auth, cases, chat working end-to-end https://github.com/virtual-ai-patient/platform/milestone/2
Medical Workflow Done May 31, 2026 Tests, diagnosis, treatment implemented https://github.com/virtual-ai-patient/platform/milestone/3
MVP Feature Complete June 30, 2026 Evaluation, debrief, analytics ready https://github.com/virtual-ai-patient/platform/milestone/4
Final Presentation July 15, 2026 MVP demo to stakeholders https://github.com/virtual-ai-patient/platform/milestone/5
Project End July 31, 2026 Documentation and handover complete https://github.com/virtual-ai-patient/platform/milestone/6

3. Month-by-Month Breakdown

Month 1: March — Foundation & Infrastructure

March Goals

  • Establish development infrastructure
  • Create working proof-of-concept
  • Set up team processes

March Key Deliverables

Deliverable Description Owner Epic
Repository Setup Monorepo structure with all directories Ilnar EPIC-00
CI/CD Pipelines GitHub Actions for backend, frontend, bot Ilnar EPIC-14
Docker Environment Local development with docker-compose Ilnar EPIC-14
Documentation README, technical description, QA docs Alina EPIC-00
Basic Chat Prototype Simple conversation with synthetic patient Aizat + Ilnar EPIC-03
Database Schema Initial design for cases and users Ilnar EPIC-13
Team Processes Tactical planning defined and adopted Alina

March Success Criteria

  • New developer can clone repo and run entire stack with one command
  • Basic chat works (user types, AI responds with synthetic data)
  • All documentation in place
  • CI passes on main branch
  • Team following weekly tactical cycle

Month 2: April — Core MVP Features

April Goals

  • User can log in and access cases
  • Full conversational patient with realistic behavior
  • Case library functional

April Key Deliverables

Deliverable Description Owner Epic
Authentication Login/signup, JWT, role-based access Ilnar EPIC-01
Case Library Case CRUD, library UI, case details Ilnar + Timur EPIC-02
Conversational Engine Full patient dialogue with emotions, progressive info Aizat EPIC-03
AI Safety Guardrails, disclaimers, monitoring Aizat EPIC-04
Database Complete All migrations, indexed queries Ilnar EPIC-13
API Layer FastAPI endpoints for all core functions Ilnar EPIC-12
Login UI Flutter screens for auth Timur EPIC-08

April Success Criteria

  • User can register, log in, and log out
  • User can browse available cases
  • User can start a case and have full conversation with AI patient
  • AI responses respect guardrails (no medical advice)
  • Conversation history saved in database

Month 3: May — Medical Workflow

May Goals

  • Add medical tests ordering
  • Capture diagnosis and treatment decisions
  • Polish frontend for realistic workflow

May Key Deliverables

Deliverable Description Owner Epic
Test Catalog 20+ common medical tests available Ilnar EPIC-05
Test Ordering UI Interface to select and order tests Timur EPIC-05
Test Results Plausible results generated per case Ilnar EPIC-05
Decision Forms Diagnosis and treatment plan submission Timur EPIC-06
Telegram Bot Basic bot functionality (chat only) Aizat EPIC-09
Frontend Polish Improved UI/UX for main workflow Timur EPIC-08
Case Authoring (Basic) Educators can create simple cases Ilnar + Timur EPIC-11

May Success Criteria

  • User can order tests during conversation
  • Test results appear and are plausible for the case
  • User can submit differential diagnosis and treatment plan
  • Telegram bot supports basic chat
  • Educator can create a new case via admin interface

Month 4: June — MVP Completion

June Goals

  • Implement automated scoring and debriefing
  • Add analytics dashboard
  • Complete all MVP features
  • Prepare for pilot testing

June Key Deliverables

Deliverable Description Owner Epic
Evaluation Engine Compare learner decisions to gold standard Ilnar EPIC-07
Debrief Generation Detailed feedback with reference solution Ilnar + Aizat EPIC-07
Case Authoring (Full) Complete tools with validation and preview Timur + Ilnar EPIC-11
Analytics Dashboard Basic analytics with export functionality Ilnar + Timur EPIC-10
Telegram Bot (Complete) Full bot functionality with tests and debrief Aizat EPIC-09
Integration Tests Full test suite for all endpoints Karim QA-REL
Load Testing Simulate 100+ concurrent users Karim QA-SCALE

June Success Criteria

  • After completing case, user receives detailed debrief
  • Scoring is consistent and matches gold standard
  • Educator can create, preview, and publish cases
  • Analytics dashboard shows learner progress
  • Telegram bot supports full workflow
  • Test coverage >70%
  • System handles 100 concurrent users without degradation
  • MVP is feature-complete

Month 5: July — Final Polish & Delivery

July Goals

  • Pilot with users
  • Bug fixing and performance optimization
  • Complete documentation
  • Deliver final presentation

July Key Deliverables

Deliverable Description Owner Epic
User Testing Pilot with 5-10 students Alina + Karim
Feedback Integration Incorporate pilot feedback All
Bug Fixing Address all critical and high-priority bugs All
Performance Optimization Final tuning based on load tests Ilnar QA-PERF
Documentation User guides, API docs, handover docs All
Final Presentation Demo script, slides, live demo Alina + All
Handover Repository clean, docs complete, code frozen All

July Success Criteria

  • Pilot users can complete cases independently
  • Feedback collected and analyzed
  • No critical bugs open
  • All documentation complete and accurate
  • Final presentation delivered successfully
  • Project handed over with clear next steps

5. Critical Path Dependencies

Dependency Affected Epics Risk Level Mitigation
LLM Token Access EPIC-03, EPIC-04 🔴 High Use local LLM or mock responses for development
Customer Data/Cases EPIC-02, EPIC-11 🟡 Medium Use synthetic data from ChatGPT
NDA / Legal Signing All (real data) 🟡 Medium Assume synthetic until signed; plan B
Team Availability (May–June) All 🟡 Medium Plan sprints around known time off
Denis Feedback Timeliness All 🟢 Low Weekly cycle accounts for feedback
Medical Expert Input EPIC-02, EPIC-07 🟡 Medium Denis to connect experts in May–June

6. Resource Planning

Team Capacity Assumptions

Role Person Availability Notes
Backend Ilnar 20 hrs/week Primary on backend, database, API
Frontend Timur 20 hrs/week Flutter web, UI/UX
Bot Aizat 15 hrs/week Telegram bot, AI prompts
PM Alina 15 hrs/week Coordination, docs, customer communication
QA Karim 15 hrs/week Testing, test automation, management

Total Team Capacity: ~85 person-hours per week

Effort Estimates by Month

Month Focus Estimated Hours Confidence
March Foundation 60 hrs High
April Core MVP 85 hrs Medium
May Medical Workflow 80 hrs Medium
June MVP Completion 85 hrs Medium
July Final Polish 60 hrs High

7. Risk Management

Top 5 Risks

Risk Probability Impact Mitigation
LLM access delayed High High Build with mock LLM; switch later
Team member unavailable Medium Medium Cross-train; “two is one” principle
Scope creep Medium High Strict MVP definition; features to backlog
Customer unresponsive Low Medium Build with synthetic data; document attempts
Medical expert availability Medium Medium Denis to secure commitments early

8. Success Metrics

Metric Target Measurement
On-time delivery 100% of monthly milestones Compare actual vs planned
Feature completion 100% of MVP features by June 30 Epic acceptance criteria
Quality <10 critical bugs at delivery Bug tracker
User feedback Positive pilot feedback Pilot surveys
Documentation 100% complete by July 31 Checklist

9. Connection to Tactical Planning

Strategic Roadmap (5 months)
    ↓
Monthly Milestones
    ↓
Epics broken into sprint goals
    ↓
Sprint goals → Daily tasks (tactical execution)
    ↓
Daily tasks → Weekly feedback (Denis)
    ↓
Feedback → Adjust next sprint
    ↓
Sprints → Monthly progress
    ↓
Monthly progress → Roadmap achieved

10. Summary: 5-Month Strategic Plan

Month Theme Key Epics Deliverable
March Foundation 00, 14, 13, 03 Working prototype, infrastructure ready
April Core MVP 01, 02, 03, 04, 12 Auth, cases, chat complete
May Medical Workflow 05, 06, 08, 11 Tests, diagnosis, treatment
June MVP Complete 07, 09, 10, 11 Evaluation, debrief, analytics ready
July Final Polish All Pilot feedback, documentation, presentation